In 1993 two wet basins, with both water storage and
flood storage, and one dry flood retarding basin were built on the
north-west corner of the golf course by Holroyd City Council to
protect 8 homes from over floor flooding and 35 from over-grund
flooding. The Golf Club contributed because the works also provide
additional water storage benefits. To minimise distruption to the
golf course, construction took only 4 months.
|