Home Page About the Trust Home Page Flood Mitigation Home Page Sustainable Water Home Page Water Quality Home Page Vegetation Home Page

PROJECT:

McCoy Park Basin

Location
The McCoy Park flood retarding basin is situated within McCoy Park at the confluence of Toongabbie and Blacktown Creeks approximately 7.5 km upstream of the Parramatta River. Immediately downstream, Greystanes Creek and Pendle Hill Creek join Toongabbie Creek so that effectively four creeks meet at what is known as the "confluence area".

Purpose
Although the original 1976-1980 design indicated that flood levels would be reduced as far as Lennox Bridge at Parramatta, the benefits occur mainly in the area immediately downstream. Channel clearing works accompanied the basin construction as far downstream as Lister Street, Old Toongabbie with later clearing as far as the second bridge on Old Windsor Road.

Catchment
The catchment draining to the basin wall has an area of approximately 31 square kilometres. The basin outlet is located approximately 2.5km downstream of Sierra Place flood retarding basin on Toongabbie Creek.

Basin Wall
The basin embankment is constructed of compacted earth fill to a maximum height of 5 metres (m) at the outlet, although the maximum height of the embankment above its foundation level is approximately 3.5 m. The embankment crest is 800 m long and 3.0 m wide. The bank slopes are 1 vertical to 4 horizontal. The capacity of the basin is 400,000 m3. The outlet structure of the basin is a 13 m wide slot with reinforced concrete side walls and base slab.

Design
The original design 100 year flood peak inflow was 319 m3/sec and peak outflow was 301 m3/sec. The basin was designed to attenuate (delay) the flood peak rather than to reduce the peak flow. This would allow floodwaters in Pendle Hill Creek and Greystanes Creek to pass before the peak discharge from the basin occurred. The current 100 year flood peak inflow is 420 m3/sec and peak outflow is 305 m3/sec.

A piped low flow system was installed during construction of the basin. This was intended to convey dry weather flows from the two tributaries, Toongabbie Creek and Blacktown Creek, beneath the floor of the basin to downstream of the basin's outlet structure. However, the pipe from Toongabbie Creek has become blocked, leading to the creation of a natural wetland in the upper bay of the basin. Parramatta City Council is currently investigating options for the future of the wetland because it cannot be readily maintained in its present form.

Construction
The detention basin was constructed by Parramatta City Council and completed in 1987. After a section of the main embankment opposite the end of Pendle Hill Creek was badly eroded during the August 1986 flood, this section was reconstructed. Channel clearing works in Toongabbie Creek downstream of the basin were carried out from 1987 to 1989.

Funding
The total cost of the project was $2.2 million which was shared between Parramatta City Council, (20%) and the State (40%) and Federal (40%) governments.







Trust logo